Activating Availability Control in the Background In the budget profile, you chose
activation type
2 (background activation) for availability control.
Background activation for availability control checks whether or not the
usage level
defined in the budget profile has been reached. If the
usage level
is exceeded, availability control is activated. You can start the batch run for availability control automatically.
In the project system, select the projects that you want to start in the batch run.
Choose
Logistics
or
For internal orders, choose
.
Enter the controlling area and the database profile. The screen
Background Activation of Availability Control for Projects
appears.
Enter data as required.
Note
Background activation of availability control logs the objects for which you activated availability control.
If you set the
Detailed Log
indicator, the system also displays all projects of the specified variant (object selection) for which you did
not
activate availability control.
To save the project selection as a variant, choose
The
ABAP: Save as Variant
screen appears.
Enter the variant name and text (meaning) and set the
Only for Background Processing
indicator.
Save the variant with
. You return to the initial screen and the system informs you that the variants were saved.
You can start the batch run for availability control using a job definition.