Easy Cost Planning for Internal OrdersTo calculate costs on an internal order, you can alternatively use Easy Cost Planning for the unit costing.
In the following modes, you can process the costing in the ways shown:
Mode |
The costing can be: |
|
|
|
|
|
|
Note
Note the following features when creating a costing for internal orders using Easy Cost Planning:
You can only plan in plan version 0.
Unit cost planning is no longer possible in overall planning.
Plan-integrated objects are not supported.
If you use a reference order when creating an internal order, and you have used Easy Cost Planning to make a calculation for this order, the same planning reference is assigned to the new internal order.
For more information on the
Order Manager,
see
Order Manager and Collective Processing of Master Data Changes
.
You have not yet carried out a unit costing on the internal order.
You can calculate costs and call up Execution Service .
Choose:
in the
Create order
mode,
or
Choose
Choose .
A dialog box with two tab strips appears.
You can now create a costing in several ways:
Choosing a Planning Form From Easy Cost Planning
Choose
Create cost estimate
to go to Easy Cost Planning. From there you can use
Choose planning form
to decide on the input help for the planning form.
Choosing a Planning Form in the Dialog Box
If you choose in the dialog box to create with a planning form, you can choose the planning form in the following ways:
On the tab strip
Create with planning form,
under
Subject area,
choose
Planning forms last used.
If no planning forms are displayed (for example, if you have not yet created a cost estimate), choose
All planning forms
or another role-specific worklist.
The system shows all planning forms from the subject area.
Double click on a planning form to go to Easy Cost Planning.
To search for a specific planning form, enter a search term and choose
Find
.
Under
With planning form
enter the technical name of the planning form and choose
Create
.
You go to Easy Cost Planning with this planning form.
For all three options the costing variant is taken automatically from the order type chosen when you created the internal order. The system enters the costing date and valuation date in the
Additional data
tab strip, but you can change these.
After you change one of the above procedures, the
Internal Order:Change:Easy Cost Planning
screen appears.
You can:
Create worklists
Display document flows for the costings
Delete costings
Subdivide costings
And so on
For more notes about what you need to take into account in Easy Cost Planning, see Planning Costs Using Easy Cost Planning .