Creating a Rack MeterWhen creating rack meter data, you must specify the plant where the rack meter is located. You can assign the meter to materials either individually or to all materials. If you have chosen to use the meter for all materials, you do not have to enter specific materials on the (rack meter) assignment screen.
For storage locations, you make assignments on an individual basis or you assign the rack meter to all storage locations. If you choose the option of using the meter for all storage locations, you do not have to enter individual locations.
Choose . This takes you to the initial screen for creating a rack meter.
Choose ENTER to access the
Create Rack Meter:Details
screen.
If you leave the
Rack meter
field blank, the system automatically proposes a number for the rack meter when you save the master data record.
If you want to create a new rack meter by copying data from a rack meter that already exists, enter the number of the rack meter which already exists in the
Rack Meter
field in the
Copy from
area of the screen. The data that is copied can be changed while creating the new rack meter.
In the
Create Rack Meter:Details
screen, enter a short description of the rack meter and enter the rack meter data:
Equipment
Unit of measure (UoM)
Plant in which the rack meter is used
Conversion factor
Number of digits
Deletion flag
Make one of the following assignments for the rack meter (if applicable):
Select
All materials
, if you want the rack meter to be used for all the materials.
Select
All stg.locs
. (all storage locations), if you want the rack meter to be used for all storage locations.
Choose
, to assign the meter to specific storage locations or materials. Enter the materials and/or the storage locations you want to in the
Create Rack Meter:
Assignment
screen. Choose
to return to the
Create Rack Meter:Details
screen.
Enter the start reading for the meter.
Save the rack meter.