Correcting Actual Times of a Work Station
Context
You want to correct the actual times of a work station for performance controlling purposes. You can perform the performance controlling using either the calculated or corrected actual times. If you want to correct the actual times, performance controlling provides special fields for this purpose.
Procedure
First enter the selection criteria, as required, by choosing the Plant and the Posting Date. For improved clarity, you can restrict your selection to a specific work station by first choosing the Department and then the Work Station in the selection criteria. The system defaults the Shift selection criterion. Choose a different shift here, as required. You can use the selection criteria Occupancy Category, Occupancy Type and Processes for further restrictions.
- You want to correct the actual working time for a work station. To do this, enter the working time in hours in the Working Time Actual Rec. (h) field in the entry for the relevant work station in the Work Stations overview table. Even if the Working Time Actual (h) field already contains an actual working time calculated by Dairy Operations, performance controlling will use the value you selected in the Working Time Actual Rec. (h) field.
- You want to correct the actual machine time for a work station. To do this, enter the machine time in hours in the Actual Machine Time Rec. (h) field in the entry for the relevant work station in the Work Stations overview table. Even if the Actual Machine Time (h) field already contains an actual machine time calculated by Dairy Operations, performance controlling will use the value you selected in the Actual Machine Time Rec. (h) field.
- Save your changes.