Function documentationDefine Asset Conclusion

 

You use this report to create a CIAP record for an asset that was built inside your company by assembling several components.

This process is an alternative to the standard controlling (PS) or project (CO) settlement process, transaction CJ88 (for WBS Elements), or transaction KO88 (for investment orders), for cases when you are not able to activate the final asset record using the standard processes.

Note Note

Only users with specific authorization can run this report. For more information about the authorization object related to this report, see Authorization Object M_ASSETFIN.

End of the note.

Prerequisites

You have defined the settlement rule for a fixed asset (AuC - Asset under Construction) in the Project Builder CJ20N transaction, in the main WBS element.

You have created and finalized a project on the SAP Easy Access screen under Start of the navigation path Logistics Next navigation step Project System Next navigation step Project Next navigation step Project Builder End of the navigation path.

You have done one of the following:

  • You have defined the number of quotas in which the government pays the ICMS credit according to the company code/business place and you have defined if the component will get immediate credit in Customizing for Cross-Application Components under Start of the navigation path General Application Functions Next navigation step Tax Declaration Framework (Brazil) Next navigation step CIAP Next navigation step Maintain Record Settings per Company Code/Business Place End of the navigation path.

  • You have defined the number of quotas in which the government pays the ICMS credit according to the country/region where the company is located and you have defined if the component will get immediate credit in Customizing for Cross-Application Components under Start of the navigation path General Application Functions Next navigation step Tax Declaration Framework (Brazil) Next navigation step CIAP Next navigation step Maintain Record Settings per Country/Region End of the navigation path.

Features

When you buy a component that qualifies for ICMS credit, you create a CIAP record for the component at the moment you post the nota fiscal. The system then checks if there is a record for the project (WBS Element, Order, Network) to which you have associated the component record. If the project does not have a record for the asset under construction (or final asset), the system creates a record with the status set to SU (Suspended).

The ICMS crediting can start immediately or it can be postponed, according to the settings you have made in the Maintain Record Settings per Country/Region customizing, in the Maintain Record Settings per Company Code/Business Place customizing, or via the BRF+.

If you choose to postpone the ICMS crediting (you do not check the Immediate Credit check-box), the system creates the CIAP record with the status set to IA (Fixing in progress - Component) and does not create any credit quotas for that record but posts the register that represents the purchase of the component to EFD ICMS/IPI.

When the asset is complete, you can create the record informing the company code, the business place, and the WBS or investment order. Note that the system only considers a project to be complete if you finish the project using the CJ20N transaction.

After you have executed the report, the system does the following:

  1. Sums any ICMS credit from the records of components with status IA that are not taking immediate credit and adds the credit to the finished asset CIAP record, changing the record status to CI: Fixing in progress completed - Resulting asset.

  2. Retires all the original CIAP records of the components.

  3. Reclassifies the short and long terms of the records.

You can reverse the conclusion of an asset, by checking the Reverse Asset Conclusion checkbox in the initial screen of the report.

Activities

To access this report on the SAP Easy Access screen, choose Start of the navigation path Logistics Next navigation step Central Functions Next navigation step Country-Specific Functions Next navigation step Brazil Next navigation step Tax Declaration Framework Next navigation step CIAP Next navigation step Define Asset Conclusion End of the navigation path.