Shop Floor Information System: Information StructuresIn the standard system, the following information structures are available in the Shop Floor Information System:
The information structures S021 through S024 are only updated when production and process orders take place.
S021 Production Order
This information structure contains the item data from the production order for material. It forms the data basis for the standard analysis of production order.
S022 Operation
The operation data from the production order for work center is updated to this information structure. This information structure provides the data basis for the standard analysis of operation.
S023 Material
The information structure S023 contains the totals records for material and forms the data basis for the standard analysis of material.
S024 Work Center
This information structure contains the totals records for work center and provides the data basis for the standard analysis of work center.
Updating of the information structures S025 and S028 is only triggered by repetitive manufacturing.
S025 Run Schedule Header
The key figures for run schedule header are updated to this information structure. This information structure also provides goods receipt statistics in repetitive manufacturing. The system updates all goods receipts to this information structure. It is also possible to update planned quantities to this info structure.
S025 forms the data basis for the standard analysis of run schedule header.
S028 Reporting Point Statistics
The key figures for reporting point statistics from the run schedule header are updated to this information structure. This provides the data basis for the standard analysis of reporting point statistics.
Updating of the information structures S026 and S027 is triggered by production and process orders and by run schedule headers.
S026 Material Usage
This information structure includes key figures for material usage and provides the data basis for the standard analysis of material usage. You can use the information structure to gain an overview of the components used.
S027 Product Costs
This Information structure forms the basis for the standard analysis of product costs. In the case of production and process orders, the system updates both planned and actual costs for the product costs. The planned costs are updated at exactly the same time as the release of the order; the actual costs are updated when completion confirmations and goods issues take place.
S029 Kanban
Important key figures from the Kanban system are updated to this information structure. This structure forms the data basis for the Kanban standard analysis.