Shop Floor Information System: Gantt DiagramYou can also use a Gantt diagram to evaluate the results of your operation analysis and production order analysis .
The Gantt diagram shows you the production orders for a selected characteristic value and graphically compares the target and the actual lead times on the time axis.
In the work center view, you can illustrate the production orders according to target and actual dates, earliest and latest dates and schedule deviations. The Gantt diagram can only be used in analyses of the information structures S021 and S022.
To call up a Gantt diagram, proceed as follows:
Position the cursor on one of the characteristic values in the list.
Select
Note
In the case of production orders that have not yet been confirmed, the bars for the target and the actual lead times are identical and are displayed in the same color.