Scheduling the Periodic Analysis

Use

When scheduling a periodic analysis, you determine the cycle in which the data is to be checked for the exceptional situation that is defined in the exception, meaning you schedule the background job. You can decide whether you want hourly, daily or weekly checks performed.

Use

If you want to schedule a periodic analysis, proceed as follows:

  1. From the information system menu, select Start of the navigation path Early Warning System Next navigation step Periodic analysis Next navigation step Schedule End of the navigation path.

  2. In the field Exception, specify the name of the exception that you want to schedule and press Enter.

  3. A window will appear for entering the cycle.

  4. Select the date/time key. The entry fields for the start date are displayed.

  5. Specify the start time.

  6. Select the field Periodic job.

  7. Select the function Period values. A dialog box appears with the possible periods (daily, weekly, etc.).

  8. Select the desired period value and select the function Save. You now return to the screen displaying the start date values.

  9. Choose Save.

Note Note

The other possibilities for defining a start date and how to proceed can be found in the document BC System Management.

End of the note.

Overview of Job

You can display a job overview for an exception. The job overview displays the background jobs for an exception and its status (planned, released, ready, active, completed, or interrupted).

From the overview list you can change the status of the job.

To branch to the job overview, proceed as follows:

  1. From the information system menu, select Start of the navigation path Early Warning System Next navigation step Periodic analysis Next navigation step Schedule End of the navigation path.

  2. In the field Exception, specify the name of the exception for which you want a job overview.

  3. Choose the Overview pushbutton.

You will then branch to the job overview screen.