Creating a Break PointYou can use this procedure to create a cost structure that deviates from the production structure.
You have entered a distribution profile in the project definition.
You have assigned the individual work breakdown structure (WBS) elements of your project to one or more grouping WBS elements.
In Command
, enter PEG03 .
The Change View "Breakpoint Maintenance": Overview
screen appears.
Choose New entries
.
Enter the required data.
You must name a WBS element or a network activity as the break point.
Choose Save
.
You can use the break point you have created as a cost assignment element. The costs of a replenishment element are now assigned to the break point instead of to the WBS element that created the requirement.