Planning Taking Account of the SequenceUse
The following functions for structuring the sequence of operations during dispatching and rescheduling are available to you in the strategy profile:
Forming the dispatching sequence
Taking account of the operation sequence in the order
Operation date check
By combining the first two functions with further strategy settings, you can ensure the following under certain conditions
that operations are dispatched to a work center in the desired sequence
that the operations for an order retain the chronological sequence defined in the order during dispatching
Features
The functions of the strategy profile are described in detail below. The required settings for selected dispatching strategies are put together in the strategy profile in the section
Actions
.
Forming the dispatching sequence
This function arranges the operations in the desired sequence during dispatching or rescheduling of a group of selected operations. You define this sequence using the sort key which you specify for the
dispatching sequence
in the strategy profile. The system then performs dispatching or rescheduling for each individual operation in this sequence. Note: The dispatching sequence enables you to define only the sequence in which the system should "process" the dispatching/rescheduling of the operations. The planned operations for the work centers may subsequently occur in another sequence, depending on the planning situation and the strategies that you have defined.
For more information on the dispatching sequence, see Defining the Dispatching Sequence .
Taking account of the operation sequence in the order
This function is only relevant for orders without (explicitly maintained) relationships, that is, for
Planned orders
Production orders
Maintenance orders for which you do not specify any relationships
The function ensures that an operation can only be dispatched after its immediate dispatched predecessor (forward planning) or before its immediate dispatched successor (backward planning) in the order.
When dispatching or rescheduling an order, the system first determines the immediate dispatched predecessor (forward planning) or immediate dispatched successor (backward planning). Based on the dispatched predecessor (successor), the system performs a forward (backward) lead time scheduling. The system recalculates the dates of
all
operations that have not been dispatched as well as all operations without capacity requirements that either follow this predecessor (forward planning) or precede this successor (backward planning). It subsequently dispatches the predecessor to be dispatched or rescheduled after its
immediate
predecessor (forward planning) or before its
immediate
successor (backward planning). The immediate predecessor or successor can be a dispatched operation, an operation not yet dispatched or an operation without capacity requirements.
Note:
A dispatched operation is an operation that has capacity requirements and, through dispatching on the planning table, the status
dispatched
. Operations with capacity requirements are relevant operations for planning using the planning table. An order can also contain operations that do not have any capacity requirements. These are
Operations that, according to the control key, are not relevant for scheduling
Operations for which the system does not determine any capacity requirements based on the control key
Operations whose capacity requirements are 0 (standard values and formulas for calculating capacity requirements are not maintained in the operation or in the work center).
Operation date check
This function performs different checks for operation dates. Among other things, the system generates a warning in the planning log if you dispatch or reschedule an operation before a
dispatched
predecessor (forward planning) or after a
dispatched
successor in the order.
Actions
The settings for selected dispatching strategies that you must perform in the strategy profile before you manually or automatically dispatch a group of selected operations are put together in the following table. For
order dispatching
, you should ensure that you select all the operations for each order to be dispatched.
Strategy profile settings for different dispatching strategies
Dispatching strategy |
Application area |
Strategy profile settings |
Generating a particular operation sequence for a work center |
|
|
Order dispatching observing the operation sequence in the order |
|
Use the corresponding sort key or sequence and layout key with the order and operation number as sort criteria for the
Further settings: See above. |
|
Use the corresponding sort key or sequence and layout key with the order and operation number as sort criteria for the
Activate
Activate
|
Relationships
You define the sort key in the menu option
Define sort key
in the Customizing function
Capacity leveling and extended evaluation
.