Checking the Capacity Availability OnlineIn order processing, you can call up the capacity availability check manually at any time. In addition to this, the system can trigger the capacity availability check automatically at order creation or order release, if you have set the system to do this in Customizing. During the capacity availability check, the system only considers the capacities that are relevant for finite scheduling.
If, during the
check
for the operations in the order, the system determines that the capacities are loaded to over 100%, the
Capacity availability
dialog box appears. Here you can:
Decide for which operations you want to confirm the capacity
Execute finite scheduling
After finite scheduling, you can decide whether you want to incorporate the new dates and confirm the capacity of the operations.
The
Capacity availability
dialog box is on the screen.
For information regarding the Customizing settings for the capacity availability check, see the section on prerequisites for the Capacity availability check .
Call up the capacity availability check in the order header.
If the system determines insufficient capacity, it takes you to the
Capacity availability
dialog box.
If you want to: |
Choose: |
Branch to the display of check results, and from there execute, if required, finite scheduling |
The
Overloaded periods, that is, periods where the capacity load exceeds the load limit, are underlined in red. |
Immediately execute finite scheduling |
The system executes finite scheduling, and the dialog box
Here the new dates and date shift for each operation are displayed in days. |
In both dialog boxes the
Capacity confirmed
indicator is set for an operation, if there is sufficient capacity available on all the capacities that are loaded by the operation; that is, if the capacity load of all capacities lie within the load limit. You can cancel this indicator at any time or set it again for any number of operations, even when capacity is insufficient.
All possible activities that you can select in the
Capacities with overload
and
Operation dates
dialog boxes are summarized in the following table:
Possible activities in the Capacities with overload dialog box
If you want to: |
Choose: |
Incorporate the displayed confirmation indicators |
The system only incorporates into the basic load the capacity requirements for operations for which the
|
Confirm capacity of all operations |
The system sets the
|
Confirm the capacity of none of the operations |
The system cancels the
|
Execute finite scheduling for an order |
The system executes finite scheduling, and the dialog box
|
Set the
|
|
Cancel the
|
|
Reset the confirmation indicator to the status before the check |
|
Possible activities in the Operation dates dialog box
If you want to: |
Choose: |
|
The system only incorporates into the basic load the capacity requirements for operations for which the
|
|
The system sets the
|
|
The system cancels the
|
Set the
|
|
Cancel the
|
|
View the dispatching log |
|
View the scheduling log |
|
Reset the operation dates and the confirmation indicators to the status before finite scheduling |
|
If you reschedule an operation that has had its capacity confirmed (for example, by scheduling the order or by shifting the operation in the planning table), prior to doing so you should cancel the
Capacity confirmed
indicator and then execute finite scheduling again. The system does not cancel the indicator automatically during scheduling or rescheduling. If you do not cancel the indicator, the basic load is no longer correct - it can even exceed 100%.