Defining a Default Completion Deadline of a Task
Prerequisites
-
You have opened the Process Development perspective in the SAP NetWeaverDeveloper Studio and have expanded your project in the Project Explorer view.
-
You have created a task.
Context
A completion deadline is the deadline before which the task must be completed. By default the task has no completion deadline. You can define a default completion deadline by defining an offset related to the task activation time or by using an expression to evaluate absolute time of type xsd:dateTime.
You have an option to set the task to an error state when the completion deadline is reached.
Procedure
Results
You have defined a default completion deadline for the task. You can select the Raise critical exception when deadline is reached checkbox if you want to raise a critical exception when the task has not been completed before the deadline is reached.