Yard Order - Tasks
Use
This function allows you to create, maintain and display a yard task from a yard order. Yard tasks are descriptions of activities that must be done for items. They are activities that model all kinds of services on the yard like unloading, moving a transportation unit (TU) to a storage place, cleaning a TU, repairing a TU. Yard tasks are the key entities for planning and execution.
After you create a yard order, you create yard tasks and assign items to the task. (For more information, see Yard Order - Items.)
Features
-
When you create a yard order, the system checks whether the default tasks are defined and if they are, then the system creates these tasks. The number of tasks may be different for inbound and outbound yard orders. You can create default tasks only for movement and non-movement activities and not for loading activities. You can delete or edit these tasks.
-
You can assign items to the yard tasks. To do so, select the item or grouping item and the yard task to which you want to assign the item. Choose the Assign option.
-
You can maintain a setting that controls whether the yard order items are automatically assigned to the default tasks or not. If you make this setting, the system always assigns all the items. You can make this setting in Customizing activity Define Default Activity Types under . Select the Item Assignment indicator.
-
You can create, edit, delete a yard task from the Tasks tab of a yard order only when the Status of the yard order is Planned.
-
You can create a yard task from the Items tab of a yard order only when the Status of the yard order is Active. You can do this only when you have entered the TU Number for the item.
-
You can delete yard tasks. To do so, select a yard task and choose the Delete option.
-
You can copy an existing yard task. To do so, select a yard task and choose the Copy option. If there are items assigned to the yard task that you are copying, the system assigns the same items to the copied yard task.
-
Sections of a yard task
-
General
-
Activity Type
Yard tasks are represented by Activity Types. It is mandatory to assign an Activity Type to a yard task.
-
Activity Category
The Activity Category defines one of the possible scenarios of yard task execution.-
Activity Category can be of the following types:
-
Movement
-
Non-Movement
-
Loading/Unloading
-
-
The system determines the Activity Category automatically once you enter the Activity Type.
-
Activity Category influences the yard item input behavior. The system determines the scenario that is executed based on the value of this field.
-
Cross-docking is not allowed in the case of Non-Movement activity category.
-
-
Status
-
Immediate Confirmation indicator
Once you activate the yard task, the system automatically confirms the yard task. You do not have to select the Start and Confirm buttons.
-
Yard Task Queue
The queue is one of the ways to manage the assignment of yard tasks to the user who is working with the yard task mobile user interface. The yard task is assigned to the queue either manually or automatically by the system.-
Manual assignment – You can enter the Yard Task Queue value manually in the yard task.
-
Automatic determination of queue – The system determines the queue when you save the yard task.
-
Automatic determination of queue runs only for yard tasks that do not have any queue assigned to them manually.
-
Automatic determination of queue is based on the Activity Type, Source Storage Type and the Destination Storage Type of the yard task. For more information, see Maintain Queue Determination.
-
-
-
Handling Resource
You can manually enter the handling resource for a yard task. In this case, the system assigns this yard task to only this handling resource in the mobile user interface.
-
Business Partner
You can assign a business partner for the yard task so that the system can execute the coordination and billing processes.
-
-
Execution (Planned)
-
Planned Start Date
This is the date on which the task is planned to start. The system defaults the date that you have entered while creating the yard order. You can edit the same. It is mandatory to enter the Planned Start Date.
-
Planned Start Time
The system defaults the time that you have entered while creating the yard order. You can edit the same. This is the time at which the task is planned to start. The system defaults the same time for all the tasks. Since you cannot execute all the tasks at the same time, change the time for the subsequent tasks. It is mandatory to enter the Planned Start Time.
-
Duration Planned
The Duration Planned is proposed by the system but you can overwrite it.
-
-
Execution (Actual)
-
Actual Start Date
This is the actual date on which the task was executed. The system determines the Actual Start Date.
-
Actual Start Time
This is the actual time at which the task was executed. The system determines the Actual Start Time.
-
Duration Actual
This is the actual duration of the task. The system determines the Duration Actual
-
-
Yard Order Number
A yard task can have reference to only one yard order with the exception of a cross docking yard task.
-
Cross Docking
In the case of cross docking, you enter the Destination Yard Order Number. Only outbound yard orders are allowed as destination yard order numbers.
-
Source
This is the source location of the yard task.-
Can be entered manually. The system proposes the actual location of the first item in the yard task.
-
It may happen that a yard task that has to be activated has no source location maintained for it. In this case, during activation of the yard task, the system automatically assigns the actual location of the yard transportation unit assigned to the first yard task item as the source location.
-
In the case of an inbound yard order, the system defaults the inbound checkpoint of the yard order as the Source. This happens only if you have maintained the Movement Direction for the Activity Type as Check-in Movement in Customizing for Define Activity Types under .
-
In the case of an outbound yard order, the system determines the source from the departure storage bin if you have maintained the Movement Direction for the Activity Type as Check-out Movement.
-
-
Destination
This is the destination location of the yard task.-
In the case of an outbound yard order, the system defaults the Destination Location of the yard order from the yard order outbound checkpoint if you have maintained the Movement Direction for the Activity Type as Check-out Movement.
-
In the case of an inbound yard order, the system determines the destination from the arrival storage bin if the you have maintained the Movement Direction for the Activity Type as Check-in Movement.
-
If you have indicated the Activity Type as relevant for subsystem, the Destination Location is determined from the subsystem.
-
If you have indicated the Activity Type as relevant for automatic destination location determination, the system determines the Destination Location based on the Customizing settings.
The location (storage bin type) should be compatible with the TU type. When you save the yard task, the system checks for this compatibility.
-
-
Predecessor and Successor
If you select the Positioning Type as Sequence (see Assign Visual Object Type to Storage Bin Type), you can maintain the predecessor or successor while creating or confirming the yard task. During yard task activation, the system validates the correctness of the predecessor and successor. During yard task confirmation, the TU is inserted in the storage bin based on the predecessor or successor that you have maintained. If you do not maintain the predecessor or successor, the TU that is moved to the storage bin is added at the end of the TU sequence.
-