Procedure documentationCalculating Overhead

 

When you save a unit cost estimate, overhead costs (overhead rates and/or process costs) are calculated automatically and inserted as items of category G (overhead rates) or X (process costs).

You can also calculate overhead rates and process costs manually, using the Calculate Overhead function.

Prerequisites

  • A costing sheet has been entered in the valuation variant.

  • An overhead key (if applicable) has been entered in the master data of the reference object, such as the material.

Procedure

  1. Go to the list screen of the unit cost estimate.

  2. Choose Start of the navigation path Functions Next navigation step Calculate Overhead End of the navigation path.

Result

Overhead rates and process costs are calculated based on the costing sheet and overhead key.

Items of category G (overhead rates) and X (process costs) are inserted.