Creating Measurement Documents

Prerequisites

Please note the following rules when creating a measurement document for a measuring point :

You can only enter a valuation code on its own when the indicator V alCode sufficient has been set in the master record of the measuring point.

Please note the following rules when creating a measurement document for a counter :

Enter either the counter reading, or the difference between the current reading and the last reading. The system will automatically calculate the other value in each case.

Procedure

To call up the individual functions in the table, choose Start of the navigation path Logistics Next navigation step Plant maintenance Next navigation step Technical objects. End of the navigation path

Function

Menu path

What you should know

Creating a measurement document directly

Start of the navigation path <FunctLocation/Equipment> Next navigation step Measurement documents Next navigation step Create End of the navigation path

You use this function for routine readings and measurements.

Creating measurement documents for several measuring points or counters simultaneously

Start of the navigation path <FunctLocation/Equipment> Next navigation step Measurement documents Next navigation step List editing Next navigation step Create End of the navigation path

You use this function if you want to create measurement documents for several measuring points or counters of a single technical object.

You can change the detail data for any selected measuring point or counter by choosing Start of the navigation path Goto Next navigation step MeasPoint End of the navigation path .

Creating measurement documents for several technical objects simultaneously

Start of the navigation path Logistics Next navigation step Plant maintenance Next navigation step Maintenance processing Next navigation step Completion confirmation Next navigation step Measurement documents Next navigation step Multiple entry Next navigation step For MeasPointObjects End of the navigation path

You use this function if you want to create measurement documents for several measuring points or counters of different technical objects.

You can change the detail data for any selected measuring point or counter by choosing Start of the navigation path Goto Next navigation step MeasPoint End of the navigation path .

Creating a measurement document for a maintenance notification

Start of the navigation path Logistics Next navigation step Plant maintenance Next navigation step Maintenance processing Next navigation step Notifications Next navigation step <Required processing mode> End of the navigation path

You can change the detail data for any selected measuring point or counter by choosing Start of the navigation path Goto Next navigation step MeasPoint End of the navigation path .

Creating a measurement document for a maintenance order

 

To call up this function, use the technical completion confirmation. You access the corresponding activity report from the order (See The Central Completion Confirmation Function ).

Creating a measurement document during order completion confirmation

 

To be able to create a measurement document for an order operation, first create an operation list for the order, then select the required operation and create the measurement document for it (See The Central Completion Confirmation Function ).