Calculating Service Lines or Composite of Service Lines

Use

You want to plan the costs for the service lines or composite of service lines. You can use the costing method Easy Cost Planning to do this.

Procedure

  1. On the service overview screen, select the BOS initial mode, an outlet level, or a service line.

  2. Choose .

    If you have not created costing yet, the screen for doing so appears. On the Additional data tab page, enter a valid costing variant and choose Transfer cost estimate .

    If you have selected a service line, this screen also appears. On the appropriate tab page, you can assign a planning form. Choose Transfer cost estimate .

    The Easy Cost Planning processing screen appears.

  3. Carry out the costing.

    For more information, see Executing Cost Planning with Easy Cost Planning .

  4. Exit costing by choosing Back .

    Caution Caution

    When you exit the Easy Cost Planning screen by choosing Back , your costing is saved temporarily. Your data is not saved to the database until you save the sales document.

    You can only save or exit costing if does not contain any errors. Choose Cancel to exit a costing that contains errors.

    End of the caution.

Result

The results of costing (including additions and deductions and overhead costs assessments) are displayed in a costing report. For more information, see Costing Report .

The basic costs of the individual costing items are grouped together to form different condition types such as material, wage, and equipment. These are transferred to the appropriate conditions in the costing sheet of the service line for sales pricing purposes. For more information, see Sales Price Determination .

You can transfer the target costs and quantities to costing for the work breakdown structure elements (WBS elements) as default values for the project execution. For more information, see Cost Transfer to the Project .