Example: Term To Date

Converts a given set of terms of cash flows into dates referencing a given start date.

The configuration allows you to choose between a default approach and an approach that applies different logic to distinguish between pattern items that are of either balance type (cumulative factor/amount values) or movement type (delta factors/amounts).

The examples below are both for patterns of type MOV (delta) and of type BAL (cumulative).

Input Data with Pattern MOV (Delta) Values

Start Date Contract ID Pattern KF Type Period Unit Period To
2019-01-01 A MOV (Delta) 6 1
2019-01-01 A MOV (Delta) 6 2
Start Date Contract ID Pattern KF Type Period Unit Period To
2019-01-06 B MOV (Delta) 6 1
2019-01-06 B MOV (Delta) 6 2
Start Date Contract ID Pattern KF Type Period Unit Period To
2019-01-01 C MOV (Delta) 6 1
2019-01-01 C MOV (Delta) 6 2
2019-01-01 C MOV (Delta) 6 3
2019-01-01 C MOV (Delta) 6 4

Flow Modeling Configuration

Rules (Tab)
Rule Description Rule Type State Rule Grouping Rule Ordering Selection
TTD Term To Date Term To Date Active      
Rule Line
Line *Line Granularity *Period Type *Start Date *Date Determinant *Day of Month *Period *Value Type *Result Date
1 Contract ID Monthly/Day of Period Start Date End of Period BLANK/25 Period To Pattern Key Figure Type Result Date

Key Configuration Description

Field Meaning Notes
Line Identifier of the line Must be unique
Line Granularity Determines the size of each partition of data Mandatory input that has to be inserted in the Granularity section of the Signature tab
Period Type Determines the final pattern structure (for example, monthly or quarterly) Mandatory input
Start Date Starting date to compute the day count Mandatory input
Date Determinant Specifies how the date is determined Mandatory input.
Codes:
  • 1 = Start of period
  • 2 = Middle of period
  • 3 = End of period
  • 4 = Actual day of period
  • 5 = Day of period
Day of Month Determines the result date if Date Determinant is set to Day of Month  
Period To Day count of the starting pattern for the cash flow Mandatory input
Value Type Can have either the value “MOV” or “BAL”, and determines which value type the cash flow item is comprised of. Ensure that the field contains these two values only. This is important because different logic is applied for movements / balance types on the first date of the resulting pattern.
Result Date The function writes the new date to this field. Mandatory output

Expected Output

Expected Output for Input MOV (Delta Values) – Period Type = Monthly

Start Date Contract ID Pattern Key Figure Type Period To Period Type *Result Date
2019-01-01 A MOV (Delta) 1 6 2019-01-31
2019-01-01 A MOV (Delta) 2 6 2019-02-28
Start Date Contract ID Pattern Key Figure Type Period To Period Type *Result Date
2019-01-01 B MOV (Delta) 1 6 2019-06-30
2019-01-01 B MOV (Delta) 2 6 2019-07-31
Start Date Contract ID Pattern Key Figure Type Period To Period Type *Result Date
2019-01-01 C MOV (Delta) 1 6 2019-01-31
2019-01-01 C MOV (Delta) 2 6 2019-02-28
2019-01-01 C MOV (Delta) 3 6 2019-03-31
2019-01-01 C MOV (Delta) 4 6 2019-04-30

Expected Output for Input MOV (Delta Values) – Period Type = Day of Period

Start Date Contract ID Pattern Key Figure Type Period To Period Type *Result Date
2019-01-01 A MOV (Delta) 1 6 2019-01-25
2019-01-01 A MOV (Delta) 2 6 2019-02-25
Start Date Contract ID Pattern Key Figure Type Period To Period Type *Result Date
2019-01-01 B MOV (Delta) 1 6 2019-06-25
2019-01-01 B MOV (Delta) 2 6 2019-07-25
Start Date Contract ID Pattern Key Figure Type Period To Period Type *Result Date
2019-01-01 C MOV (Delta) 1 6 2019-06-25
2019-01-01 C MOV (Delta) 2 6 2019-07-25
2019-01-01 C MOV (Delta) 3 6 2019-03-25
2019-01-01 C MOV (Delta) 4 6 2019-04-25

Input Data with Pattern BAL (Cumulative) Values

Start Date Contract ID Pattern Key Figure Type Period Unit Period To
2019-01-01 D BAL (cumulative) 7 0
2019-01-01 D BAL (cumulative) 7 1
2019-02-01 E BAL (cumulative) 11 0
2019-02-01 E BAL (cumulative) 11 1
2019-02-01 E BAL (cumulative) 11 2
2019-02-01 E BAL (cumulative) 11 3

Flow Modeling Configuration

Rule Line
Line *Line Granularity *Period Type *Start Date *Date Determinant *Day of Month *Period *Value Type *Result Date
1 Contract ID Quarterly Start Date End of Period   Period To Pattern Key Figure Type Result Date

Expected Output for Input BAL (Cumulative Values) – Period Type = Quarterly

Start Date Contract ID Pattern Key Figure Type Period Unit Period To Result Date
2019-01-01 D BAL (cumulative) 7 0 2019-01-01
2019-01-01 D BAL (cumulative) 7 1 2019-01-31
2019-02-01 E BAL (cumulative) 11 0 2019-02-01
2019-02-01 E BAL (cumulative) 11 1 2019-03-31
2019-02-01 E BAL (cumulative) 11 2 2019-06-30
2019-02-01 E BAL (cumulative) 11 3 2019-09-30