Migration of Customizing Projects

Procedure

To migrate customizing projects from older systems into the current system:

  1. Choose Start of the navigation pathSystem Next navigation step Services Next navigation step ReportingEnd of the navigation path.

  2. Enter the program name MIGRATE_PROJECT_NEW.

  3. Choose Start of the navigation pathProgram Next navigation step ExecuteEnd of the navigation path.

  4. Enter the project number of the old Customizing project which you want to copy into the current system.

  5. Choose Start of the navigation pathProgram Next navigation step ExecuteEnd of the navigation path.

    The application component hierarchy is displayed in a window.

  6. Choose the application component for the new customizing project.

  7. Choose Continue.

    The project IMG for the new customizing project is generated.

Result

The complete contents of a customizing project from a Release 3.0, 3.1, 4.0 or 4.5 R/3 System are copied into the current release.