Defining and Executing a New Mass Change Procedure for Background Execution

Use

This processing mode permits you to specify a date and time when the mass change procedure is executed. You typically specify background execution if the number of changes to be made is large and online execution might result in time delays.

For example, you can schedule background execution overnight or on the weekend, when there are no employees present in the office.

Procedure

  1. If you wish to load a mass change template, specify it in the Template ID field.

  2. In the Background Execution field, select Yes.

    The system displays the steps of the mass change procedure in the Procedure Overview assignment block.

  3. Choose the Select Contracts step, and specify the criteria of the contracts you wish to change:

    • The selection criteria appears in the Select Contract Header assignment block.

    • The search results appear in the Result assignment block.

    • For more information on using the search, see Search Tool for the Select Step

  4. Move to the next step.

    Alternatively, if no additional step is available, select New and specify the required node and operation. For example, if you wish to add a new rights scope, select Rights Scope in the Node field, and select Add in the Operation field.

    Depending on the operation and node associated with the step, different assignment blocks appear beneath, allowing you to specify additional details associated with the step:

    • The form view assignment block displays the details of the operation to apply. For example, if you are adding a rights group, the system displays fields were you can specify the details of the rights group to add.

    • The list view assignment block is applicable only for procedures configured for online execution – it typically displays the contract nodes on which the operation is to be applied.

  5. Make your specifications for the step in the form view assignment block.

  6. Repeat steps 4 and 5 until you have made all the required specifications for the procedure.

  7. When you are finished, select Execute in Background. The Schedule Job dialog box appears.

    Specify the following information and select the Start button:

    • Whether the procedure is to start immediately or later

    • The start date and time, if you indicate that the procedure is to start later

  8. To view the results of mass change procedures carried out by way of background execution, you can refer to the mass change log. For more information, see Mass Change Logs.

Notes on Mass Change Procedures Configured for Background Execution

  • You can save the mass change procedure as a mass change template.

  • If changes are made to the contracts between the time of the mass change procedure definition and the scheduled run, the search results obtained during the run might be different.