What's New Viewer - SAP S/4HANA

Confirmation Settings for Discrete and Process Manufacturing

This feature enables you to further refine confirmation profiles with settings dependent on plant and order type. The Customizing activities Define Confirmation Parameters and Define Single-Screen Entry for Confirming Production Orders or Define Single-Screen Entry for Confirming Process Orders can be linked to each other.

Technical Details

Type

New

Functional Localization

Not applicable

Scope Item

1BM (Make-to-Order Production - Semifinished Goods Planning and Assembly), BJ5 ( Make-to-Stock Production - Discrete Manufacturing), BJ8 (Make-to-Stock - Process Manufacturing Based on Process Order), BJE (Make-to-Order Production - Finished Goods Sales and Final Assembly), BJH (Make-to-Stock Production - Repetitive Manufacturing)

Application Component

PP-SFC-PLN

Available As Of

SAP S/4HANA 1909

Additional Details

In the Customizing activity for single-screen entry, you can define a standard profile with a nearly empty screen for confirmations. This screen will be displayed until you enter a confirmation number or an order and operation number in the confirmation application.

In the Customizing activity for confirmation parameters, you assign a confirmation profile to a specific combination of plant and order type containing the desired layout and settings.

If you now select the new checkbox Use Profile for Plant/Order Type in the Customizing activity for single-screen entry, the system searches for a confirmation profile specific for the combination of plant and order type given by the confirmation number or order number that you enter in the confirmation application.

The system will then display your defined layout and settings.

Type of change New/changed Customizing activity How to find it What you can do Leading scope item
New field in Customizing activity Define Confirmation Parameters Start of the navigation pathProduction Next navigation step Shop Floor Control Next navigation step Operations Next navigation step ConfirmationEnd of the navigation path Define a confirmation profile dependent on a plant and an order type. BJ5 ( Make-to-Stock Production - Discrete Manufacturing)
New fields in Customizing activity Define Single-Screen Entry for Confirming Production Orders Start of the navigation pathProduction Next navigation step Shop Floor Control Next navigation step Operations Next navigation step Confirmation Next navigation step Single-Screen Entry End of the navigation path Define how the system determines the confirmation profile to be used for single-screen entry of confirmations. BJ5 ( Make-to-Stock Production - Discrete Manufacturing)
New fields in Customizing activity Define Single-Screen Entry for Confirming Process Orders Start of the navigation pathProduction Planning for Process Industries Next navigation step Process Order Next navigation step Operations Next navigation step Confirmation Next navigation step Single-Screen EntryEnd of the navigation path Define how the system determines the confirmation profile to be used for single-screen entry of confirmations. BJ8 (Make-to-Stock - Process Manufacturing Based on Process Order)