Maintaining Data For SchedulingWhere Can You Maintain Data for Scheduling?
You maintain... |
In the following tab page |
normal/minimum duration for internal activities |
|
duration for general costs activities |
|
duration for external activities |
|
Constraints |
|
Indicator: Earliest/latest |
|
reduction strategy for internal activities |
|
Note
You enter the offset to start and finish for activity elements on the detail screens for work and general costs, and on the overview screen for external elements.
Starting Scheduling
To start scheduling, proceed as follows:
Call up a network.
Choose
or
.
Scheduling is started.
Changing Scheduling Parameters
You can change some of the settings that you make in Customizing for scheduling in the applications by choosing
Adjust
basic dates
indicator. Set this indicator if you want the basic dates to be adjusted to the scheduled dates if the scheduled dates lie outside the time frame of the basic dates.
Shift network
indicator. Set this indicator if you do not want the actual dates of partially confirmed activities to be taken into consideration when the network is rescheduled.
Start in past
: Number of days that the scheduled start may be in the past.
Max. redctn. level
: Maximum reduction level used to reduce lead time.
See also: