Time ConstraintsYou can specify time constraints for the start and finish of an activity. When you schedule a network, the system takes the constraints on the start and finish dates and times that you specified into account.
The table shows which time constraints can be entered for start and finish dates:
Activity start |
Activity finish |
Must start on... |
Must finish on... |
Cannot start before ... |
Cannot finish before... |
Cannot start later ... |
Cannot finish later... |
Start from resource planning |
Finish from confirmation |
You can also specify, using a key, whether earliest dates or latest dates are used for the activity . If you set the
earliest/latest
key, the earliest dates are the same as the latest dates and the activity does not have a float.