Configuration of Personal Needs, Fatigue, and Unavoidable Delays using BRFplus

You can configure the calculation of standard time to take personal needs, fatigue, and unavoidable delays (PFD) into account.

Labor Management must be active so that the system creates executed workloads for warehouse activities.

If you want to use PFD when calculating the adjusted planned duration (or standard time), you can so in the following ways:

In the standard system, the BRFplus function designed for PFD calculation is /SCWM/LM_PFD. You can find it in BRFplus application /SCWM/LM_PFD_SYS.

You can create one or more rulesets which subscribe to PFD calculation BRFplus function.

As import parameters, the BRFplus function context contains data from the following sources:

  • Executed workload (EWL)

  • Processor attributes, such as ID, service start date, processor type

  • Shift, if an assignment between processor and shift exists

  • Exception codes entered at time of execution

The result elements in the context are the PFD factor and the PFD allowance.

The system uses the Business Add-In (BAdI) Decision Service for PFD Calculation (/SCWM/EX_LM_PFD_DSM) to calculate the PFD factor and the PFD allowance. For more information, see Customizing for Extended Warehouse Management under Start of the navigation pathBusiness Add-Ins (BAdIs) for Extended Warehouse Management Next navigation step Labor Management Next navigation step Personal Needs, Fatigue, and Unavoidable Delays Next navigation step BAdI: Decision Service for PFD CalculationEnd of the navigation path.

Example Ruleset

When working in BRFplus, you can use the example ruleset for PFD in the customizing application /SCWM/LM_PFD_CUST to create the PFD factor.

The example ruleset contains one rule as an example for each aspect of PFD:

  • Personal factor based on service start date of processor

  • Fatigue factor based on the working hour from shift

  • Allowance time for unavoidable delays based on entered exception codes

The adjusted planned duration from previous determinations of the normal time is multiplied by the PFD factor. For more information about determinations of normal time, see Determination of Normal Time Using Engineered Labor Standards and Travel Distance Calculation.

You can also use the ruleset to define a PFD allowance. The PFD allowance is time that the system adds to the adjusted planned duration. The system takes the time unit from the workload or the warehouse number.