Activity Output Planning
When activity planning, you can determine the quantity-based output of one or more cost centers and activity types using different planning dimensions such as price and capacity. By creating multiple plan versions, you can compare different plan values before deciding on a final plan.
For more information about the business process for activity type planning, see Activity Type Planning.
You have selected the controlling area and stored it in your user parameter.
You have made the settings for the Cost Center Manager
(SAP_CO_COSTCENTER_MANAGER
) role or the Internal Controller
(SAP_CO_INTERNAL_CONTROLLER
) role in Customizing under .
You can use the Cost Center: Activity Output
and Price Planning
(FCOM_IP_CC_ACTOUTPUT01
) Web Dynpro application configuration to facilitate activity output
planning. For cost centers and activity types, this application configuration
allows you to plan the activity output and the manual prices by fiscal
year and by period. When you start planning, you can select a version,
a fiscal year, a period interval, one or more cost centers, and activity
types.
You can choose the planning phase you what to use, for
example, fiscal year or period. You can plan activity output quantities
(Planned Quantity
and Capacity
) and manual prices (Price
(Fixed)
and Price (Variable)
) using the controlling area currency by fiscal year or by period.
Regardless of the posting period you select, the entry
fields, Planned Quantity
and Capacity
, always represent the totals of the whole
fiscal year. Entry fields Price (Fixed)
and Price (Variable)
contain the
average period prices (total of prices for all periods divided by
number of periods). The system distributes the entered value for Planned Quantity
and Capacity
to the selected posting periods when you save or move to another
planning screen in the same stack. Due to the average computation
method of entry fields Price (Fixed)
and Price (Variable)
, all entered
values are distributed in a similar way to all posting periods defined
for the fiscal year.
If you change a value, the delta value of the change is distributed. The distribution is done in an analog way so if the selected posting periods have zero value, the delta value is distributed equally. Otherwise, the delta value is distributed by the ratio of period values. You can also distribute the value manually.
Caution
With personalization, you can change the way the planning
screens are arranged, for example, you can change the stacking so
that planning screens appear below each other or in several stacks.
If you change the screens so they display across several stacks and
move to a screen belonging to another stack after you change yearly
values, you must distribute the values manually by choosing Distribute
to see the effect of a yearly value change
on period distribution.
When planning by period, you can change the period-based distribution of your plan value. To simplify the planning process on period level, the application configuration offers you the following planning queries:
Planning query to enter the planned quantity and capacity on a period-based level
Planning query to enter the fixed price and variable price on a period-based level
Planning query to enter the planned quantity, capacity, fixed price, and variable price on a period-based level
Using the appropriate query makes this period-based planning process much more transparent and easy to use.
You can copy previous plans and create multiple plan versions to allow you to compare different plan values before deciding on a final plan.
You can use Copy from Reference
to copy data from a reference plan to create a new version of the
plan. For example, you can copy data from a plan for the previous
planning period as a basis for your current planning period.
In addition, you can use Revaluate Quantities
and Revaluate Prices
to increase
plan values by a certain percentage. For example, you can create multiple
versions for the same period, use different quantities and prices
in each version, and compare the versions to determine which plan
gives you the largest percentage increase.