Scheduling by Factory CalendarIf you create a monthly maintenance cycle (one month = 30 days) and have specified scheduling by factory calendar, planned dates are calculated as follows:
Current Date |
21. August, 1999 |
1st planned date |
02. October, 1999 |
2nd planned date |
15. November, 1999 |
3rd planned date |
02. January, 2000 |
The planned dates therefore have an interval of 30 working days . In this example, five days of the week have been defined as work days in the factory calendar.