Scheduling by Factory Calendar

If you create a monthly maintenance cycle (one month = 30 days) and have specified scheduling by factory calendar, planned dates are calculated as follows:

Current Date

21. August, 1999

1st planned date

02. October, 1999

2nd planned date

15. November, 1999

3rd planned date

02. January, 2000

The planned dates therefore have an interval of 30 working days . In this example, five days of the week have been defined as work days in the factory calendar.