Integration
Financial plans contain the information required to support downstream processes in order to avoid duplicate data entry and to provide the efficiencies and benefits of an integrated solution.
The following integration scenarios are possible from Project Cost and Revenue Planning
(CA-CPD-FP
):
Scenario/Transfer Method | Transfer Rationale |
|---|---|
Quantity Update in Network Activity | Transfer of work quantity from |
Material Component Update in Network Activity | Creation of the material component and the transfer of the material quantity from |
Cost Update in Network Activity | Transfer of the cost values related to the work and material quantities at the cost element level. The transfer of cost supports processes such as results analysis legacy |
Cost and Revenue Update in Work Breakdown Structure Elements (WBSEs) | Transfer of cost and revenue values from |
Update of Resource Management Information in | Transfer of planned items from |
Update of cost and revenue to WBS elements (for phases and tasks) in cProjects | Transfer of planned costs and revenues to WBS elements that are assigned to phases or tasks in a cProject. |