Approval Process
The approval process of change requests in Project Issue and Change Management
is managed through activities.
In the standard system, SAP delivers the following activity categories for the definition of approval activity types and activity templates:
Approval activity
Cost planning activity
In the standard system, SAP delivers the following activity types:
CR1
: Cost Planning Activity
EAA
: External Approval Activity
IA1
: General Activity
IAA
: Internal Approval Activity
UPA
: Update Activity
IA2
: Change Request Alternative (note: this is a technical activity and must not be used to create activity templates)
In the standard system, SAP delivers the following activity templates:
ICMACT
: General Activity Template
ICMALT
: Change Request Alternative (note: this is a technical template and must not be deleted or be used to create activities)
ICMUPD
: Update Activity Template
EXTAPPROV
: Send for Customer Approval
INTAPPROV
: Internal Approval
Create a cost estimation alternative to plan costs for the change request (type CRC
).
Create a cost planning activity (activity type CR1
).
Plan the details of the change in the change planning workbook of the Project Cost and Revenue Planning
application.
Mark the status of the cost estimation alternative as ready for approval.
Note
When multiple cost estimation alternatives exist for a change request, you can only mark one as ready for approval.
The cost of the change corresponding to the cost estimation alternative marked as ready for approval, is the value that is considered in the Pending Costs
column in the Project Cost Status
report.
Mark the status of the cost planning activity as complete.
Upon saving the object, the system automatically creates an internal approval activity for the change request and assigns an employee responsible according to the rules defined in Business Rule Framework plus
(BRFplus).
The system sends an e-mail notification to the employee responsible.
The employee responsible approves the internal approval activity.
Upon saving the object, the system creates an external approval activity for the change request and assigns an employee responsible according to the rules defined in BRFplus.
The system sends an e-mail notification to the employee responsible.
Note
The employee responsible can forward this e-mail to an external approving authority or the customer, as a manual task. Since this e-mail is intended for external recipients, Project Issue and Change Management
provides a PDF attachment with the required details. For more information, see Customizing for Project Issue and Change Management
under .
The approving authority or the customer sends the approval to the employee responsible.
The employee responsible updates the status of the external approval activity. When the external approval activity is approved, the system marks the status of the cost estimation alternative from Ready for Approval
to Approved
.
Note
The cost of the change corresponding to the cost estimation alternative marked as approved, is the value that is considered in the Approved Costs
column in the Project Cost Status
report.
The system marks the change request as approved and also updates existing forecasts with the approved quantities and costs.
If you have assigned any purchase order as a reference object to the change request, the system updates the purchase order, if you have activated the Business Add-In BAdI: Updating of Purchase Orders with Additional Quantities
(/PICM/BADI_UPDATE_DOCUMENT
). This BAdI allows you to add material quantity in existing purchase orders (POs) by using approved change requests. This BAdI checks the PO for the original quantity, based on the reference object assigned to the change request. For the addition of an approved material quantity, a new line item is added in the PO.