Creating Line ItemsYou have the required roles and authorizations.
Financial plans linked with master project structures (also known as execution structures) are available in the system.
SAP BusinessObjects Analysis, edition for Microsoft Office
is installed on your system.
You have defined the business objects for master project structures in Customizing for SAP Commercial Project Management
under .
You have made the following settings in Customizing for SAP Commercial Project Management
under :
Define Plan Scenarios
Define Resource Types
Define Resources
Define Plan Types
Select the Financial Plan Item ID
cell.
In the Select Member
dialog box, select the required financial plan item, such as a work breakdown structure element (WBSE).
Repeat these steps for Resource Type
, Resource
, UoM (Unit of Measure)
, and Transaction Currency
.
Enter the required quantity for each month.
On the Analysis
ribbon, in the Financial Planning
group, choose Calculate
.
If all characteristics of subordinate nodes are the same, recalculating aggregates the quantities of these subordinate nodes at all superordinate nodes in the hierarchy. These values are displayed as summary records at the superordinate node level.
You can also create a number of line items and then recalculate all at once.
To revert to the earlier calculations, on the Analysis
ribbon, choose Back
and To Previous Saved State
.
On the Analysis
ribbon, in the Planning
group, choose Save Data
to transfer the data to the InfoCube.