Copying with References
Use
You can use this procedure to copy plan data from a reference structure, into a bid structure or a master project strucuture.
Prerequisites
-
You are authorized to edit financial plans.
-
Master projects, with master project structures (also known as execution structures), exist in the system.
-
You have a bid structure or a master project structure into which you want to copy plan data from a reference structure.
Procedure
-
Launch a financial plan and choose Edit.
-
In the Copy from Reference section, search for the relevant reference plan structure and plan version.
The plan structure is displayed in the Reference Structure table.
-
Select the plan version to which you want to copy structure elements from the reference structure.
-
Select a structure element from the plan structure and the reference structure. You can also search for the relevant nodes in both the structures.
-
Choose Link to create a logical link between the selected structure elements.
-
Choose to copy the line items and the planned data (such as resource type, resource, cost, comments, and so on) from the structure element in the reference structure.
-
Choose to copy the following:
-
Data that was planned for the selected structure element or actual data recorded against the accounting object for the structure element
-
Data relevant to all or a selected few resource types
-
Data corresponding to key figures for the selected resource types
-
Comments
-
-
Choose Save to save the plan structure and the copied data to the planning cube. For more information, see Planning Cube.