Copying with References

Use

You can use this procedure to copy plan data from a reference structure, into a bid structure or a master project strucuture.

Prerequisites

  • You are authorized to edit financial plans.

  • Master projects, with master project structures (also known as execution structures), exist in the system.

  • You have a bid structure or a master project structure into which you want to copy plan data from a reference structure.

Procedure

  1. Launch a financial plan and choose Edit.

  2. In the Copy from Reference section, search for the relevant reference plan structure and plan version.

    The plan structure is displayed in the Reference Structure table.

  3. Select the plan version to which you want to copy structure elements from the reference structure.

  4. Select a structure element from the plan structure and the reference structure. You can also search for the relevant nodes in both the structures.

  5. Choose Link to create a logical link between the selected structure elements.

  6. Choose Start of the navigation pathCopy Next navigation step CopyEnd of the navigation path to copy the line items and the planned data (such as resource type, resource, cost, comments, and so on) from the structure element in the reference structure.

  7. Choose Start of the navigation pathCopy Next navigation step Advanced CopyEnd of the navigation path to copy the following:

    • Data that was planned for the selected structure element or actual data recorded against the accounting object for the structure element

    • Data relevant to all or a selected few resource types

    • Data corresponding to key figures for the selected resource types

    • Comments

  8. Choose Save to save the plan structure and the copied data to the planning cube. For more information, see Planning Cube.