Period-End and In-Period Forecasting

Project Cost and Revenue Planning allows you to forecast with the following period options:

Period-End Forecasting

In-Period Forecasting

With this feature, you can forecast for future periods, based on actuals till the forecast period (last period).

You can track the overall forecast status of the process by activating it at the plan scenario level and assigning a forecast status profile to the plan scenario in Customizing for Start of the navigation pathProject Cost and Revenue Planning Next navigation step Define Plan ScenariosEnd of the navigation path.

With this feature, you can provide forecast values (for example, ETC value) even for the current period (for example, up to a cut-off date in the current month). This feature can typically be used to revise forecast values for specific structure elements that need frequent forecast revision, due to the nature of the activity or shorter life cycles (for example, a few weeks).

The cut-off date specifies the date until which the system considers actual postings for a forecast.

You can specify the workbooks relevant for in-period forecasting at plan type level in Customizing for Start of the navigation pathProject Cost and Revenue Planning Next navigation step Define Plan TypesEnd of the navigation path.

Forecasts are based on the following planning functions:

  • Forecast based on actuals

  • Forecast based on constant EAC

Forecasts are based on the following planning functions:

  • Forecast based on actuals

  • Forecast based on constant EAC