Cost Settlement Chains
When you construct assets, you can charge the costs of the materials and services to various objects (asset master records, WBS elements, networks, or CO orders).
The basic procedure is described in Construction of Fixed Assets. It describes how you charge all costs to an “intermediate” asset master record, and then, when you capitalize the asset, transfer the costs to a “real” asset master record. You can however charge costs to objects other than an intermediate asset. The following describes which permutations the system supports.
To be able to settle line items from CO objects periodically to
intermediate asset master records for assets under construction, you must
have set the investment profile that you use to Line item settlement
and list of origins.
You can do so in Customizing for Investment
Management
(IM), by choosing Note that you do not
need to use IM itself.
You have created the asset master records as described in Creation of Master Data for Asset Construction.
The cost settlement chains that are supported are as follows:
Goods issue to asset under construction → Full settlement to real asset
Goods issue to WBS element → Periodic settlement to asset under construction → Full settlement to real asset
Goods issue to CO order/network → Periodic settlement to asset under construction → Full settlement to real asset
Goods issue to CO order/network → Period settlement to WBS element → Periodic settlement to asset under construction → Full settlement to real asset
Direct invoice posting to asset under construction → Full settlement to real asset
Direct invoice posting to WBS element → Periodic settlement to asset under construction → Full settlement to real asset
Direct invoice posting to CO order/network → Periodic settlement to asset under construction → Full settlement to real asset
Invoice posting to CO order/network → Period settlement to WBS element → Periodic settlement to asset under construction → Full settlement to real asset
Goods issue to asset under construction → Full settlement to asset under construction → Transfer to real asset
Goods issue to WBS element → Periodic settlement to asset under construction → Full settlement to asset under construction → Transfer to real asset
Goods issue to CO order/network → Periodic settlement to asset under construction → Full settlement to asset under construction → Transfer to real asset
Goods issue to CO order/network → Periodic settlement to WBS element → Periodic settlement to asset under construction → Full settlement to asset under construction → Transfer to real asset
Direct invoice posting to WBS element → Periodic settlement to asset under construction → Full settlement to asset under construction → Transfer to real asset
Direct invoice posting to CO order/network → Periodic settlement to asset under construction → Full settlement to asset under construction → Transfer to real asset
Direct invoice posting to CO order/network → Periodic settlement to WBS element → Periodic settlement to asset under construction → Full settlement to asset under construction → Transfer to real asset