Creating Connections Between Selected Actions
Prerequisites
You have opened a Process Integration scenario. The Process Integration scenario contains at least two actions.
The following three situations are possible for defining a connection between two actions - with one specific connection type resulting from each.
-
If both actions follow each other directly in the same application component, then you can define a Sequence between both of those actions.
-
If both actions belong to different application components and communicate synchronously with each other, then you can define a Synchronous Connection . In this case, both actions have to be at the same level in the Process Integratio scenario graphic.
-
If both actions belong to different application components and communicate asynchronously with each other, then you can define a Asynchronous Connection . The follow-on action must be one level deeper than the source action for this.
Context
You can create a Connection between two actions.
Procedure
-
Select both actions in the graphical work area of the Process Integration Scenario Editor .
-
In the context menu, choose Create Connection between Selected Actions .
The Display/Edit Connections editor appears. You can make further entries here.
-
Choose Copy .
Results
A connection is added between both actoins and displayed as a polygon in the Process Integration scenario graphic.