ProductionOrders_Stages Object Members
See Also  Overview 

Public Methods

Public Method AddAdds a new data line to the object.
Public Method DeleteDeletes the current line.

Returns a result value that indicates success or failure.

Public Method SetCurrentLineSets the active row to a specified row number.

Public Properties

Public Property CalculationProportionThe percentage of resource capacity that will be consumed in a particular route stage.

Field name: RtCalcProp.

Public Property CountReturns the total number of records in the table.
Public Property DocEntryThe internal ID of the production order.

Field name: DocEntry.

Public Property EndDateThe latest date by which a component needs to be used in the production process.

Field name: EndDate.

Public Property NameThe stage name.

Field name: Name.

Length: 100 characters.

Public Property RequiredDaysThe number of days required for a specific Resource to complete the Planned Qty. of a particular route stage.

Field name: ReqDays.

Public Property SequenceNumberThe sequence number that is assigned to each route stage.

The sequence indicates the precise order in which the routing stages must be performed during the production process.

Field name: SeqNum.

Public Property StageEntryThe internal ID of the stage.

Field name: StgEntry.

Public Property StageIDThe stage ID.

Field name: StageId.

Public Property StartDateThe earliest date on which the component is needed in the production process.
For a production order that has route stages, the Start Date for the first Route Stage type line (included in the calculation) is set to the production order header Start Date. And by default, the Start Date for the next Route Stage type line is the same as the calculated End Date of the previous route stage.
You can manually change the Route Stage type line Start Date to any date that falls between or is equal to the production order header Start Date and Due Date.

Field name: StartDate.

Public Property StatusThe production order stage status.

Field name: Status.

Public Property WaitingDaysThe number of days to wait after the completion of the route stage. This field will not be visible by default. As soon as a Route Stage type line is created, you can manually enter the number of waiting days.

Field name: WaitDays.