Calendar Event Statuses

During their lifecycle, SAP Analytics Cloud calendar events have different statuses. Use this reference to find out which statuses are available and under which circumstances an event receives a specific status.

Statuses for Events with Assignees

Processes, composite tasks, general tasks, review tasks, input tasks and manual data locking tasks can have the following statuses:

Status Description
Inactive The event definition isn't finished yet. Only owners can see it, and no notifications are sent.
Open The event is visible to all users. Either the assignee hasn’t opened it yet, the start date has not yet been reached, or the owner reopened the event.
In Progress The start date has been reached and the assignee has opened the event. Assignees or reviewers are currently working on it.
In Review This status is only available for input tasks. All assignees submitted their work or declined to work on the task and the creator/reviewer is currently checking the numbers. In the Details panel, the input task is displayed as Declined or Submitted.
On Hold The assignees and the reviewers can’t work on the event. It is blocked due to one of the following reasons:
  • Blocked by a dependency: A review task is on hold as long as the preceding general task hasn't been accomplished, for example.

  • Another user suspended the event, its parent event, or all its child events (if it's a process without assignees).

Partially Accomplished The event is finalized. This status only applies to multi-step events like composite tasks or processes: Some of the steps are accomplished and some are canceled.
Accomplished The assignee successfully finished his or her work.
Canceled

The owner canceled the event, or the assignee declined to work on the task.

This status is also displayed for users who have been removed from the event and therefore can’t see most of the information anymore.

Statuses for Automatic Events

Data action tasks, automatic data locking tasks, and publications can have the following statuses:

Status Description
Inactive The event definition isn't finished yet. Only owners can see it, and no notifications are sent.
Open The automatic event is waiting for the start date.
In Progress The automatic event has been triggered and is currently being executed.
On Hold The automatic task is blocked due to one of the following reasons:
  • The permission request is pending, the assignee hasn't agreed yet.

  • The assignee has declined the permission request. The owner can assign someone else.

  • The assignee has withdrawn their agreement to run the automatic task with their permission. The owner can assign someone else.

Partially Successful Some steps of the automatic event were executed successfully while others failed.
Successful All steps of the automatic event were executed successfully.
Failed None of the automatic event's steps were executed successfully.
Canceled The automatic event has been canceled due to one of the following reasons:
  • The owner canceled the event.

  • If a recurrence is set and preceding occurrences are still running at start date, the event has been canceled automatically.

  • If a data action is canceled, corresponding multi action tasks or data action tasks will be canceled, as well.

  • If the owner doesn’t start the permission request or the assignee doesn't agree to run an automatic task with their permission before the task's start date, the task will be canceled automatically.