Working with the Planning Result 
Use
The planning result display allows you to adjust and test the result.
Prerequisites
You have either:
Procedure
Function |
How to call up function |
What you should know |
Hide and show header details for the material |
|
The header details point to various tab pages for master data and movement data for the material selected. You define the sequence of the tab pages in Customizing for MRP under Define Screen Sequence for Header Details. |
Enter or display material memo |
|
Next to the symbol for the material memo the name and date of the last change are displayed. |
Display the exception message |
Position the cursor on the exception message and choose |
|
Display additional data for the MRP element. |
|
|
Activate period totals display |
|
|
Change procurement proposal |
Double-click the procurement proposal |
In the lower section of the screen is an area with the data of the procurement proposal selected and here you can make your changes. Copy the changes with The procurement proposal is firmed automatically. Firmed procurement proposals are not adjusted in the planning run. Note also the firming logic of the master production scheduling (see
Firming Type ). |
Reschedule procurement proposal |
Position the cursor on the procurement proposal and choose |
If the system issues a rescheduling proposal for the procurement proposal, the procurement proposal is automatically rescheduled to this date. If the system does not issue a rescheduling proposal, a dialog box appears in which you can enter the MRP date desired. |
Add procurement proposal |
|
After you have defined the type of procurement proposal, you can enter the relevant data in the lower section of the screen. If you choose Enter, the stock/requirements situation changed by the procurement proposal is visible immediately. Transfer the data with |
Delete procurement proposal |
Position the cursor on the procurement proposal and choose |
|
Add/change production order |
|
This function is only available in single-level single-item planning and in interactive planning. |
Change or add components of a planned order |
Double-click the planned order and choose Goto ® Maintain material components or Enter material components. |
This takes you to the component processing. Here, you can:
|
Explode BOM again |
Double-click the planned order and choose Goto ® Explode BOM |
The BOM is exploded again and the component processing appears. |
Check availability of the components of a planned order |
Double-click the planned order and choose Goto ® Check availability |
|
Plan capacity for material |
Double-click the planned order and choose Goto ® Capacity planning ® Capacity leveling ® Material view |
The indicator for scheduling in the initial screen of planning must be set so that lead time scheduling is carried out. For further information on capacity planning see the SAP document PP-Capacity planning. |
Plan capacity for planned order |
Double-click the planned order and choose Goto ® Capacity planning ® Capacity leveling ® Order view. |
See above |
Print planning result |
|