Show TOC
Maintain
Materials Cumulation for Routes
In order to plan shipments it is not always
necessary to know all the details of the material / delivery items that are to
be transported. For example, it is often irrelevant to know whether two
delivery items are made up of 500 litres of red and 500 litres of green paint
and sufficient to know that 1000 litres of paint need to be planned as
shipment goods. Similar circumstances exist in the batch handling area where
different batches of one material are divided up between several delivery
items.
Delivery items can be combined together
according to different criteria in order to provide a better overview and to
reduce the volume of data to be transmitted.
- Combining or deleting delivery items depending
on how transportable they are.
- Combining items with the same freight
codes.
You can configure the combination (cumulation)
for each combination of transportation planning point and route separately in
the maintenance transaction. However they can also be configured together for
one transportation planning point.
Both cumulation procedures have the following
effects:
- Reducing transportable materials:
Activating this function by clicking on the relevant table field
affects:
- the cumulation of a material's batch items in
each header item
- the cumulation of a material's product
selections in each header item
- Deletion of text and value items
- Deletion of BOM items not relevant to
movement.
- It is not possible to determine the freight
code set as this has to be predefined for the transportation/route
combination. In this way the freight code can be determined together with the
material freight group from the material master. The items in a delivery are
cumulated according to freight code, whereby the material category is only
represented in the message by its freight code. The quantities are still
available in weight and volume specifications but no longer as number of
pieces, etc.
If both cumulation procedures are activated,
the cumulation according to shipment relevant items is executed before the
freight code - related cumulation.
In this IMG activity you can maintain the
planning restriction with the following resources:
- Maintain individual entries in material
cumulation for the transportation planning point or a combination of
transportation planning point and route.
- Enter route areas in the table (mass
transaction)
- Copy route areas in the table if
transportation planning point has changed (mass transaction)
Activities
- Maintain material cumulation
a) Select the
transportation planning point to be processed.
b) If you wish
to maintain the cumulation for a route, enter the route. If you wish to
maintain the cumulation for all the shipments in the transportation planning
point, leave the route field blank.
c) If you wish
to activate the cumulation according to freight code, enter the required
freight code set. If you do not enter a freight code set, the cumulation will
be deactivated.
d) If you wish
to activate a shipment relevant cumulation, click on the relevant button.
- Enter route areas in the table (mass
transaction)
Entering route areas is appropriate if you wish to carry out the same material
cumulation for several routes. In the selection screen enter a transportation
planning point and the routes for which you would like to add entries in the
table. For each new entry you can configure a freight code set and activate
the shipment relevance. You can use a switch to select whether existing
entries for the transportation planning point should remain or be
overwritten.
- Copy route areas with changes to
transportation planning point (mass transaction)
Copying route areas is appropriate if you have several planning systems with
the same material cumulation defaults and you just wish to copy the defaults.
Specify the transportation planning point and the routes whose entries you
would like to copy. You also need to specify to which transportation planning
point the entries should be copied. You can use a switch to select whether
existing entries for the transportation planning point / route should remain
or be overwritten.