Requirements Grouping with Grouping WBS Elements for Each Plant 
Use
You use this procedure if you would like to group material requirements of different WBS elements in a plant using several
grouping WBS elements.This is useful, for example, if you want to group WBS elements in a plant according to certain criteria. You can thus group the WBS elements according to specific criteria and plan the material requirements accordingly in every plant.

In plant 1, all WBS elements from projects with ordering parties from the public sector are to be assigned to grouping WBS element 1 and all WBS elements from projects with ordering parties from the private sector to grouping WBS element 2.
Prerequisites

If you would like to group the WBS elements according to two criteria, such as ordering parties from the public sector/ private sector, you create one grouping WBS element for each grouping criterion in the plant.
Features
In material requirements planning, every material in a plant that is allowed to be planned with requirements grouping, is planned with the grouping WBS element that has been assigned the WBS element, which has caused the material requirement. However, this is only possible if you have assigned the MRP groups of the material to the grouping WBS element.
Example
MRP Procedure
The system combines the requirements of the assembly A, which are caused by the WBS elements E1 and E2, and creates a procurement element for these requirements that is assigned to the account of the grouping WBS element.
The system calculates the requirements of the assembly A, which are caused by the WBS elements E3, and creates a procurement element for these requirements that is assigned to the account of the grouping WBS element D2.

If you have not assigned the WBS element, which has caused the material requirement, to the grouping WBS element, individual project planning is carried out for the material with reference to the WBS element. The procurement element is then assigned to the account of the WBS element.

When planning an assembly across plants, that is, for example procured using stock transfer or production in an alternative plant, the dependent requirements are in the planning plant (plant 1) and in the delivering plant/production plant (plant 2). If you have only assigned the grouping WBS element in plant 1, which has been assigned the WBS element of the assembly, to the MRP group in plant 1, then only the requirements in plant 1 are planned with the grouping WBS element from plant 1. This is because plant 2 is unable to determine an assignment for the requirements. In this case, you also have to assign the WBS element from plant 1 to the grouping WBS element of plant 2.