Multi-Plant Requirements Grouping with Single Grouping Element 

Use

You use this procedure if you would like to combine the requirements for all materials using a single grouping WBS element. At the same time, you can use this grouping WBS element in all plants.

Prerequisites

Features

In material requirements planning, every material that is allowed to be planned with requirements grouping is planned with the grouping WBS element. The individual requirements that are caused by the WBS elements are combined and the system creates a procurement element, which is assigned to the account of the grouping WBS element, for every material.

In MRP evaluations, an individual MRP segment is displayed for the grouping WBS element.

If there are material requirements that are caused by a WBS element, such as, for example, reservations, and this WBS element has not been assigned to the grouping WBS element, the system then carries out individual project planning. The material is planned for the WBS element and procured with reference to the WBS element.