Show TOC

(K_CSKB_PLA)

Definition

This authorization object protects cost element planning in Cost Center Accounting.

Defined Fields

The fields of this authorization object are:

The cost elements are protected via their key.
The protected planning activities are:

Examples

The following authorizations, which are combined in one profile, are stored in your user master:

Author.. Control... CElm Activity
1 0100 * 03
2 0400 0000400000,
00004001* 02, 03
3 TEST * *

Authorization 1:

In controlling area 0100, you are authorized to display the planning of all cost elements.

Authorization 2:

In controlling area 0400, you are authorized to display and change the planning of cost element 0000400000 and of all cost elements in the interval from 0000400100 to 0000400199.

Authorization 3:

In controlling area TEST, you can plan the cost elements as you like. You are authorized for all planning activities without restriction of cost elements.

Further Notes

The cost element planning is secured through several authorization objects:

you can arrange which cost centers may be planned through the general authorization object for the cost center accounting ( K_CCA ). (The authorization object K_CSKS_PLA is obsolete. Here you need to give the all-authorization.)

over the general authorization object for internal orders ( K_ORDER ), you can arrange which internal order may be planned.

over the authorization object CO: Cost element planning ( K_CSKB_PLA ), you can arrange the cost elements which can be planned. Here you should give extensive authorizations and further restrictions over object K_CCA and K_ORDER.

you can secure various plan versions over the authorization object CO: Version ( K_KA09_KVS) through the user defined authorization groups.

over the authorization object CO: Planer profile ( K_TKA50 ), you can secure the existing planner profiles. You can create a detailed authorization allocation for the recording of plan data through the combination of authorization groups and default, read-only parameters.