C_PRPS_PRC Profit center

Definition

You can use this authorization object to control who can access WBS elements in the Project System depending upon the profit center assigned to the WBS element.

The system checks the authorization:

Defined Fields

The authorization object contains the following fields:

The following values are used for the actions:

Examples

User A may change WBS element L-400/10, which is assigned to profit center P34-80, as well as plan dates and costs for it. Relevant authorizations: