Determining and Assigning Storage Locations to the MRP Area 
Use
You assign goods receipt and issue elements to an MRP area using the receiving storage location in the case of receipt elements, and using the issuing storage location in the case of the issue elements.
Prerequisites
Features
Assigning the Receipts and Issue Elements to an MRP Area
The receipt elements (planned orders, purchase requisitions and so on) are assigned using the receiving storage location, which the system determines during the planning run. The receiving storage location is displayed in the MRP list or the stock/requirements list in the column Storage location or it is displayed in the procurement element itself, for example, in the header data of a planned order. The system checks whether the receiving storage location that has been determined belongs to the MRP area. If this is the case, the system assigns the receipt element to the MRP area.
The issue elements (planned independent requirements, sales orders, dependent requirements, reservations) are assigned via the issuing storage location, which the system determines during the planning run. The issuing storage location is displayed in the MRP list or the current stock/requirements list in the column Storage location as well as in the component list of the planned order.

If the system is unable to determine a storage location, the system assigns the receipt or issue element to the plant MRP area.
Determining the Storage Location for Receipt Elements
You can maintain the receiving storage location for a material on various screens in the system:
The system determines the storage location as follows:

In the case of external procurement, the system does not take into account any production version, which may be available, when determining the storage location.
An assembly is assigned to two MRP areas of the storage location type and can be manufactured on two different production lines (line 1 and 2). You have therefore created two production versions for the assembly:
version 1 with production line 1 and the receiving storage location 0001
version 2 with production line 2 and the receiving storage location 0002
You have defined one MRP area each for both storage locations and you have created the MRP area segments in the material master.
During the planning run, the system determines the production version on the basis of its settings that is valid for the procurement proposal, for example, production version 1. In doing so, the system assigns the receipt element to the MRP area of the storage location 1.
An assembly with two different MRP areas is manufactured on a production line. You have therefore only created one production version. In this case, you are not allowed to maintain storage locations in the production version, as otherwise it would always be assigned to the same MRP area.
Determining the Storage Location for Issue Elements
The system determines the storage location for the issue of components during the BOM explosion in the planning run. The system proceeds as described in
Storage Location Determination in BOM Explosion.The storage location found determines the assignment to the MRP area.