Message Transmission in Direct Production
Use
If a planned order for direct production, which has been changed manually and is therefore firmed, is changed or deleted by the next planning run, the MRP controller responsible must be notified of the change as soon as possible. The MRP controller receives an e-mail with the information about the change automatically.
Prerequisites
Features
The system sends an e-mail if a planned order for direct production is changed or deleted or if the BOM had to be re-exploded.