Maintain Payment Program Parameters
Use
You need to identify a payment run with a name. Then you have to determine the company codes and vendors for which you want to trigger the payment program. The date of the next payment run is also important for deciding whether to pay with cash discount or to pay net. Once this has been done, a payment proposal list can be automatically generated according to the terms of payment in the documents.
Procedure
Menu Path |
Accounting ® Financial Accounting ® Accounts Payable ® Periodic Processing ® Payments |
Transaction Code |
F110 |
Field |
Europe |
North America |
Run date |
Today’s date + 10 days |
Today’s date + 10 days |
Identification |
Any 5-character identifier |
Any 5-character identifier |
The system displays the status No parameters entered as yet.
Field |
Europe |
North America |
Company codes |
1000 |
3000 |
Pmnt meths |
SU (S=Check, U=Transfer) |
C (Check) |
Next p/date |
Today’s date + 30 days |
Today’s date + 30 days |
Vendor (from/to) |
1000 to 1005 |
3000 to 3725 |

If more than one person has been working with this vendor, more items may be selected in the payment proposal list in addition to those seen in the previous transaction.

The system checks the due dates of all items for the vendors you selected for payment processing. With reference to the date of the next payment run, the system decides which items are to be paid so that no discount is lost.
Field |
Europe |
North America |
Vendors from/to |
1000 to 1005 |
3000 to 3725 |
On the Automatic Payment Transactions: Status screen, the status is Parameters have been entered.