Show TOC
Define Database
Selection Profiles
All data in the information system comes from
or is derived from the logical Project System database (PSJ).
You need the profile for this database for all
analyses in the Project System.
In the database profile, you
determine:
- the project view according to which the
selected data is displayed on the screen, for example, sorted according to
profit center.
- the maximum explosion level for the
selection.
The level of detail
depends on the project view and the selection criteria.
Example: You select
the following objects in the database:
- a work breakdown structure that has five
hierarchy levels
- a network, including subnetworks, that has
four hierarchy levels.
You maintain 5 as a
maximum level. In this case, the network objects will not be displayed in the
information system.
- the objects that are selected in the
database.
Notes
Once you are within an analysis, you cannot
select any more objects from the database.
You determine the scope of selection on the
relevant initial screens.
Standard
Settings
Database profiles are available with the
standard R/3 System.
Activities
1. Create a
database profile.
2. Enter the
database profile in the overall profile.