Show TOC
Create Profile
for Project Version
You require profiles for project versions if
you are working with status-dependent project versions:
You stipulate the following in the
profiles:
- The objects which appear in the project
version, such as WBS elements, activities, PRT, or costs
- User and/or system statuses which trigger the
storage of a project version
- The version key for the project
version
You can define as many user and/or system
statuses in a profile as you want.
Example
In the profile, you have stipulated that a
project version is created when the Released status
is set.
The system then creates a project version each
time an object which is to appear in the project version is
released.
- When you release a network, a project version
is created showin all the objects defined in the profile.
- When you release a version-relevant activity
in the network, this activity is entered in the project version.
Standard
Settings
We do not delivery any profiles for project
version in the standard system.
Activities
1. Enter the
key and name for a profile.
2. Select the
objects which are to appear in the project version.
3. Maintain
system and/or user statuses for the profile.
4. Save your
data.
5. Enter the
project version profile in the network profile and project
profile.