Maintain Budget Profiles

In this step, you

To be able to budget projects, you must create a budget profile or use an existing one.

The following parameters are relevant for project budgeting:

Here you define:
In the project budget profile, the "Overall" indicator, working in conjunction with the "Releases" indicator, has the following effect:
Ind. "Overall" Ind. "Releases" Avail. control against...
X X Released overall budget
- X Released annual budget
X - Overall budget
- - Annual budget
The activation type controls availability control. There are three activation types:
0 = cannot activate
This activity type may cause an already active availability control to be deactivated.
1 = automatic activation when budget is assigned
You must maintain at least one tolerance limit for the budget profile.
2 = background activation when percentage of consumption is exceeded
You must enter a percentage of consumption in background activation. The percentage of consumption represents the relationship of committed funds to the budget as a percentage.
You must maintain at least one tolerance limit for the budget profile to have the system check the posting.
Note
Additional information

Activity

1. Use "Details" to check the standard budget profiles delivered with the system.
2. Change the detail settings for the budget profiles or create budget profiles using "New entries".

Additional information

You can assign a budget profile to a project