Maintain Progress Version

In this step, you maintain the progress version. You define the control data for POC/earned value calculation.

You enter this setting separately for each company code.

Recommendation

Use the standard progress version.

Activities

1. In the section General Version Definition, create a CO version with only the usage progress analysis.
2. Save this version.
3. Select the version and choose Project Progress Analysis Settings.
1. Enter the control data for the progress version and choose Save.