In this step you can define procurement indicators for frequently used combinations of settings for procurement, so that you do not have to always enter these settings.
The indicator combines the following parameters:
You can set a procurement indicator for every component in the component overview. Alternatively, you can define a default value in in the network profile. Once assigned, procurement indicators cannot be changed.
You often generate planned independent requirements, that is preliminary requirements for stock materials, whereby these are to be kept in project stock.
To do this you enter a purchase order indicator with priority 1 for project stock, set the preliminary requirements indicator and choose the item category L (stock item).