Show TOC

Maintain report assignment from the planning board

In this activity, you stipulate which hierarchy reports you can access from the project planning board using the report/report interface.

Activities

1. Specify the application class KP for projects.
2. Specify a controlling area. Regardless of what you enter, the assignments are by report, not by controlling area.
3. Create report type project report.
4. Specify the technical name of the report you want to add as the receiver report.

Further Notes

From the project planning board, you can only access reports from the application KP with report category drilldown and report type project report.

Transport

The settings made here must be transported manually. Create a transport request with table TRSTI . Maintain the following fields:

STOOL TR
SAPPL KP