Maintain Assignment of Cost Element Group

In this activity, you define cost elements for cost element groups used in evaluation for earned values by cost element and stipulate the default cost element.

The percentages of completion (POCs) calculated for an original cost element group are recorded in summarized form under the relevant cost element; you can evaluate them in the information system. This procedure means you can make various analyses of the POCs.

Activities

1. Enter a controlling area as the work area.
2. Choose New entries.
3. Specify the following:
a) Cost element under which the POC is recorded.
The cost element must have cost element type 61.
b) Cost element group containing the basis values
4. Select the Def indicator.
If the indicator is not set, the POCs are recorded under this cost element at basis values and not by cost element.